Every deadline after a job ends runs from one date: the day the contract ended. Enter it, pick the law that governs your employment, and the dates that matter are worked out against today.

In short

Under the federal law a final settlement is due within 14 days of the contract ending (Article 53). A claim must be brought within two years of the end of the employment (Article 54(9), as amended in 2024). Other regimes differ: 10 days and a three-month claim limit for domestic workers, 14 days in the DIFC, and 21 days in ADGM.

Final settlement due by
—

Counted from the end of the contract, not from visa cancellation.

  • Enter the date the employment ended—
Your dates

The deadlines, and where each comes from

Payment deadlines and claim time limits by regime.
RegimeSettlement dueTime limit for a claimSource
Federal law14 days2 yearsFederal Decree-Law No. 33 of 2021, Articles 53 and 54(9)
Domestic workers10 days3 monthsFederal Decree-Law No. 9 of 2022, Articles 19(9) and 26(2)
DIFC14 daysset by DIFC lawDIFC Employment Law No. 2 of 2019
ADGM21 calendar daysset by ADGM lawADGM Employment Regulations 2024

The calculator counts the day after the employment ended as day one. That matches the worked example the ADGM Registration Authority gives for its own 21-day rule: a last day of 9 July means payment by 30 July.

The two-year limit

Until 2024 the labour law barred claims after one year. Federal Decree-Law No. 9 of 2024, in force from 31 August 2024, amended Article 54. Clause 9 of the amended article provides that claims concerning rights under the decree-law are not heard after two years from the termination of the employment relationship. Some official pages written before the change still mention one year, so the cautious plan is to act well inside the first year.

The 30-day unemployment insurance window

If you were insured under the Involuntary Loss of Employment scheme and lost your job other than by resigning, the claim must be submitted within 30 days of the end of the employment relationship, or of the resolution of a labour dispute. See unemployment insurance after job loss.

Deadlines that do not run from the end date

Dates are only as good as the end date

If the date your contract ended is itself disputed — pay in lieu against garden leave, or a termination letter dated differently from your last day — every deadline moves with it. Keep the letter. This tool counts calendar days and does not adjust for weekends or public holidays.

Questions

How many days does an employer have to pay the final settlement in the UAE?

Fourteen days from the end of the contract, under Article 53 of Federal Decree-Law No. 33 of 2021. ADGM allows 21 calendar days and the domestic workers law 10 days.

How long do I have to file a labour claim in the UAE?

Two years from the end of the employment relationship under Article 54(9) of the labour law, as amended by Federal Decree-Law No. 9 of 2024. Domestic workers have three months.

Does the 14 days start when my visa is cancelled?

No. It runs from the end of the contract. Visa and work-permit cancellation is a separate process.