Settlement deadline calculator
Every deadline after a job ends runs from one date: the day the contract ended. Enter it, pick the law that governs your employment, and the dates that matter are worked out against today.
Under the federal law a final settlement is due within 14 days of the contract ending (Article 53). A claim must be brought within two years of the end of the employment (Article 54(9), as amended in 2024). Other regimes differ: 10 days and a three-month claim limit for domestic workers, 14 days in the DIFC, and 21 days in ADGM.
Counted from the end of the contract, not from visa cancellation.
- Enter the date the employment ended—
The deadlines, and where each comes from
| Regime | Settlement due | Time limit for a claim | Source |
|---|---|---|---|
| Federal law | 14 days | 2 years | Federal Decree-Law No. 33 of 2021, Articles 53 and 54(9) |
| Domestic workers | 10 days | 3 months | Federal Decree-Law No. 9 of 2022, Articles 19(9) and 26(2) |
| DIFC | 14 days | set by DIFC law | DIFC Employment Law No. 2 of 2019 |
| ADGM | 21 calendar days | set by ADGM law | ADGM Employment Regulations 2024 |
The calculator counts the day after the employment ended as day one. That matches the worked example the ADGM Registration Authority gives for its own 21-day rule: a last day of 9 July means payment by 30 July.
The two-year limit
Until 2024 the labour law barred claims after one year. Federal Decree-Law No. 9 of 2024, in force from 31 August 2024, amended Article 54. Clause 9 of the amended article provides that claims concerning rights under the decree-law are not heard after two years from the termination of the employment relationship. Some official pages written before the change still mention one year, so the cautious plan is to act well inside the first year.
The 30-day unemployment insurance window
If you were insured under the Involuntary Loss of Employment scheme and lost your job other than by resigning, the claim must be submitted within 30 days of the end of the employment relationship, or of the resolution of a labour dispute. See unemployment insurance after job loss.
Deadlines that do not run from the end date
- Challenging a MOHRE decision. Where the Ministry decides a claim of up to 50,000 AED, either side has 15 working days from being notified to bring the matter before the Court of First Instance (Article 54(3) as amended).
- Registering a referred case. A worker whose complaint MOHRE refers to the labour court must register it with the court within 14 days of the referral being approved, according to the UAE Government portal's summary of Ministerial Resolution No. 47 of 2022.
- Notice before leaving for an employer's breach. A worker relying on Article 45(1) must notify MOHRE fourteen working days before leaving.
If the date your contract ended is itself disputed — pay in lieu against garden leave, or a termination letter dated differently from your last day — every deadline moves with it. Keep the letter. This tool counts calendar days and does not adjust for weekends or public holidays.
Questions
How many days does an employer have to pay the final settlement in the UAE?
Fourteen days from the end of the contract, under Article 53 of Federal Decree-Law No. 33 of 2021. ADGM allows 21 calendar days and the domestic workers law 10 days.
How long do I have to file a labour claim in the UAE?
Two years from the end of the employment relationship under Article 54(9) of the labour law, as amended by Federal Decree-Law No. 9 of 2024. Domestic workers have three months.
Does the 14 days start when my visa is cancelled?
No. It runs from the end of the contract. Visa and work-permit cancellation is a separate process.
Related
- The 14-day rule in fullWhat an employer may and may not wait for